๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
PCDC Impact Way Extension Phase III
Impact Way, Pflugerville, TX 78660, Pflugerville, TX, 78660
Completed100%
๐Project Metrics
TDLR #TABS2023009363$2.4M
Project Value
6,000
Square Feet
$401/sqft
Cost/SqFt
10 months
Duration
Registered:Jan 13, 2023
Start:Apr 1, 2022
Target:Jan 31, 2023
๐
Project Closed
Project has been completed and closed
๐Scope of Work
The scope of work includes 1000 linear feet of 4-lane public roadway with 6 foot sidewalks and wheel chair ramps at driveway crossings on both sides of the roadway.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 13, 2023
Construction Start
April 1, 2022
Expected Completion
January 31, 2023
๐Related Projects
๐คSame Owner
$8.3M total๐๏ธSame Design Firm
$10.9M totalProperty Owner
๐ค
Pflugerville Community Development Corporation
Contact: Amy Madison
2 projects ยท $8.3M
3801 Helios Way, Suite 130, Pflugerville, Texas 78660
Design Firm
๐๏ธ
DCS Engineering
3 projects ยท $10.9M
1101 S. Capital of Texas Hwy., Bldg. G-100, Austin, Texas 78746