📋Project Registered🏗️ New Construction💵 This project is privately funded, on private land for private use.

Clear Creek Storage Center, Phase II

8799 Highway 198, Payne Springs, TX 75156, Payne Springs, TX, 75156
Pre-Construction15%

📊Project Metrics

TDLR #TABS2023023075
$150K
Project Value
3,900
Square Feet
$38/sqft
Cost/SqFt
3y 2mo
Duration
Registered:Jul 7, 2023
Start:Aug 1, 2023
Target:Sep 1, 2026
Remaining:255 days
📋

Project Registered

Project has been registered with TDLR and is in pre-construction phase

📋Scope of Work

Mini warehouse

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
July 7, 2023
Construction Start
August 1, 2023
Expected Completion
September 1, 2026