Inspection Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
TTI Renovations
8201 Ewing Halsell, San Antonio, TX 78229, San Antonio, TX, 78229
Final Inspection85%
๐Project Metrics
TDLR #TABS2024000238$400K
Project Value
3,000
Square Feet
$133/sqft
Cost/SqFt
3 months
Duration
Registered:Sep 6, 2023
Start:Oct 2, 2023
Target:Dec 29, 2023
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Renovations to Transplant Institute Mezzanine Level and Level 2. Renovations to MHST Level 1 Bulk Storage.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 6, 2023
Construction Start
October 2, 2023
Expected Completion
December 29, 2023
๐Related Projects
Property Owner
๐ค
Methodist Healthcare System of SA LTD LLP
Contact: Amanda Stephens
8026 Floyd Curl, San Antonio, Texas 78229
Design Firm
๐๏ธ
Marmon Mok Architects
4 projects ยท $27.4M
1020 NE Loop 410 Suite 201, San Antonio, Texas 78209