๐Ÿ“Review Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

MID-CITY PROJECT CITY OF PHARR

1501 MIDCITIES DR., Pharr, TX 78577, Pharr, TX, 78577
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024005264
$200K
Project Value
4,800
Square Feet
$42/sqft
Cost/SqFt
6 months
Duration
Registered:Nov 13, 2023
Start:Jan 1, 2024
Target:Jun 28, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

A 4,800 SQ. FT. FACILITY CONSISTING OF: 5 OFFICES, RECEPTION, WAITING, BRAK ROOM, MEN & WOMEN TOILETS, WORK SHOP

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 13, 2023
Construction Start
January 1, 2024
Expected Completion
June 28, 2024