โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Fat Burger Huebner Oaks

11075 I.H. 10 Suite 306 suite 306, San Antonio, TX 78230, San Antonio, TX, 78230
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024006670
$200K
Project Value
1,650
Square Feet
$121/sqft
Cost/SqFt
8 months
Duration
Registered:Dec 5, 2023
Start:Dec 26, 2023
Target:Aug 15, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Remodeling the finishes such as New flooring, replacing ceiling tiles, and painting walls. Installing new kitchen equipment in existing locations.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 5, 2023
Construction Start
December 26, 2023
Expected Completion
August 15, 2024