๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Phase 13 Street Reconstruction
Gates Drive, The Colony, TX 75056, The Colony, TX, 75056
Construction50%
๐Project Metrics
TDLR #TABS2024009887$262K
Project Value
221,720
Square Feet
$1/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Jan 23, 2024
Start:Mar 31, 2024
Target:Aug 7, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction of Gates Drive from Paige Road to Baker - Reconstruction of Pemberton Lane from Mayes to Blair Oaks - Reconstruction of Mayes Drive from Pemberton to Strickland
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 23, 2024
Construction Start
March 31, 2024
Expected Completion
August 7, 2025