Brock ISD | New Elementary School
FM 1189 and Pritchard Road, Brock, TX 76087, Brock, TX, 76087
Final Inspection85%
๐Project Metrics
TDLR #TABS2024010412$49.8M
Project Value
116,936
Square Feet
$426/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Jan 30, 2024
Start:Mar 18, 2024
Target:Jul 11, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Brock ISD | New Elementary School
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 30, 2024
Construction Start
March 18, 2024
Expected Completion
July 11, 2025
๐Related Projects
๐คSame Owner
$66.5M total๐๏ธSame Design Firm
$18.7M totalProperty Owner
๐ค
Brock ISD
Contact: Mike McSwain
2 projects ยท $66.5M
410 Eagle Spirit Lane, Brock, Texas 76087
Design Firm
๐๏ธ
Huckabee
4 projects ยท $18.7M
801 Cherry Street Ste. 500, Fort Worth, Texas 76102