โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

NE ASR Enhanced Arroyo Phase 1

McCombs Street - 1 mile north of US-54 west of Painted Dunes Desert Golf Course, El Paso, TX 79934, El Paso, TX, 79934
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024011776
$6.3M
Project Value
1,001,880
Square Feet
$6/sqft
Cost/SqFt
4 months
Duration
Registered:Feb 16, 2024
Start:Feb 22, 2024
Target:Jun 22, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

The project infrastructure is planned to construct an enhanced arroyo starting from the right-of-way at McCombs going west for appx 3500 LF. The project includes landscaing amenities with a hike and bike trails.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 16, 2024
Construction Start
February 22, 2024
Expected Completion
June 22, 2024

Quick Actions

TDLR ID: TABS2024011776

Property Owner

๐Ÿ‘ค
EPWater
Contact: Scott Reinert
1154 Hawkins Blvd., El Paso, Texas 79925

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
ECKHARD K,FENNIG
RAS #476
5788 N MESA ST, EL PASO, TX 79912