โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Sam Forse Collins Recreation Area-Phase 1B

Route 255, Prv Rd 6065,, Burkeville, TX 75932, Burkeville, TX, 75932
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024016150
$1.5M
Project Value
43,560
Square Feet
$34/sqft
Cost/SqFt
6 months
Duration
Registered:Apr 15, 2024
Start:Oct 1, 2024
Target:Mar 31, 2025
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

New playground, sidewalk, parking, landscape and utilities to serve these. Renovations include update finishes and fixtures to the existing restroom and shade pavilion.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 15, 2024
Construction Start
October 1, 2024
Expected Completion
March 31, 2025

Quick Actions

TDLR ID: TABS2024016150

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
GEORGE A,PATTERSON
RAS #503
PO BOX 8616, FORT WORTH, TX 76124