๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Mueschke 9

Draper Rd. To FM 2920, Tomball, TX 77377, Tomball, TX, 77377
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024017323
$4.8M
Project Value
8,000
Square Feet
$603/sqft
Cost/SqFt
1 months
Duration
Registered:Apr 30, 2024
Start:Sep 2, 2024
Target:Sep 30, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New construction of 8,000 LF of Concrete Boulevard street, concrete sidewalks, storm sewer and roadside swales (7.25 acres)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 30, 2024
Construction Start
September 2, 2024
Expected Completion
September 30, 2024