๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Birchway Sanger
1501 West Chapman Dr., Sanger, TX 76266, Sanger, TX, 76266
Construction50%
๐Project Metrics
TDLR #TABS2024023514$59.0M
Project Value
307,604
Square Feet
$192/sqft
Cost/SqFt
2 years
Duration
Registered:Jul 22, 2024
Start:Nov 1, 2024
Target:Oct 31, 2026
Remaining:315 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of a 306 unit multifamily project with approximately 280K net rentable SF. There will also be a single story clubhouse and swimming pool.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 22, 2024
Construction Start
November 1, 2024
Expected Completion
October 31, 2026
๐Related Projects
๐คSame Owner
$87.2M totalProperty Owner
๐ค
Greystar Development Central LLC
4 projects ยท $87.2M
600 E. Las Colinas Blvd. STE 2100, Irving, Texas 75039
Design Firm
๐๏ธ
Meeks Partners
4 projects ยท $165.2M
16000 Memorial Dr. STE 100, Houston, Texas 77079