๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Tyler ISD Golf Training Facility
2850 W Shaw St., Tyler, TX 75701, Tyler, TX, 75701
Completed100%
๐Project Metrics
TDLR #TABS2024023698$3.0M
Project Value
1,927
Square Feet
$1.56K/sqft
Cost/SqFt
8 months
Duration
Registered:Jul 23, 2024
Start:Sep 1, 2024
Target:May 3, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
A new golf facility building for Tyler ISD.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 23, 2024
Construction Start
September 1, 2024
Expected Completion
May 3, 2025