๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Kyle FM 1626 Pump Station - Main

5155 FM 1626, Kyle, TX 78640, Kyle, TX, 78640
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024024070
$4.7M
Project Value
9,400
Square Feet
$500/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Jul 26, 2024
Start:May 23, 2024
Target:Apr 26, 2026
Remaining:127 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

9400 SF new pump station building. Building is unmanned pump station with a restroom, control room, pump room, electrical and storage room.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 26, 2024
Construction Start
May 23, 2024
Expected Completion
April 26, 2026

Quick Actions

TDLR ID: TABS2024024070

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
JEFFREY A,GUTKNECHT
RAS #472
9958 FM 428, AUBREY, TX 76227