๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SH 95 (CSJ: 0323-01-028)

From: SL 230 To: South of FM 535, Smithville, TX 78957, Smithville, TX, 78957
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025000299
$606K
Project Value
48,138
Square Feet
$13/sqft
Cost/SqFt
3y 11mo
Duration
Registered:Sep 5, 2024
Start:Jan 2, 2026
Target:Oct 31, 2029
Remaining:1412 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Upgrade from a 2 lane rural to a 3 lane urban including a continuous left turn lane. Pedestrian-related elements include: sidewalks, curb ramps, handrails, and pedestrian signals.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 5, 2024
Construction Start
January 2, 2026
Expected Completion
October 31, 2029

Quick Actions

TDLR ID: TABS2025000299

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201