๐Project Registered๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Stonebrook Circle Bldg 1 Shell
Block A, Lot 3 & 4, Frisco, TX 75034, Frisco, TX, 75034
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025003280$1.2M
Project Value
15,908
Square Feet
$75/sqft
Cost/SqFt
9 months
Duration
Registered:Oct 15, 2024
Start:Nov 1, 2024
Target:Aug 1, 2025
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Building Shell Construction
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 15, 2024
Construction Start
November 1, 2024
Expected Completion
August 1, 2025
๐Related Projects
๐คSame Owner
$3.5M total๐๏ธSame Design Firm
$1.5M totalProperty Owner
๐ค
Stonebrook Circle LP
Contact: Allen Gandy
3 projects ยท $3.5M
2626 Stonebrook Parkway Ste. 100, Frisco, Texas 75034
Design Firm
๐๏ธ
Abaya Design Studio
4 projects ยท $1.5M
215 S. Denton Tap Road Suite # 215 Suite # 215, Coppell, Texas 75019