๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Pearl Street Intersection Improvements

Intersections of Pearl St at Flora St and Pearl St, Dallas, TX 75201, Dallas, TX, 75201
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025004180
$2.8M
Project Value
35,000
Square Feet
$79/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Oct 28, 2024
Start:Mar 3, 2025
Target:Aug 30, 2026
Remaining:251 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

2 intersection improvements including street paving, sidewalk paving, traffic signal improvements (~35,000SF)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 28, 2024
Construction Start
March 3, 2025
Expected Completion
August 30, 2026

Quick Actions

TDLR ID: TABS2025004180

Property Owner

Design Firm

๐Ÿ›๏ธ
Kimley-Horn
4 projects ยท $40.0M
225 E John W. Carpenter Freeway, Suite 1100, Dallas, Texas 75062

Registered Accessibility Specialist

๐Ÿ“‹
SHARLYNN L,KEYS
RAS #418
512 KEYES RD, SUNSET, TX 76270