๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
DFW III-II Building 3 Tenant Fit Out
501 Austin Blvd, Red Oak, TX 75154, Red Oak, TX, 75154
Construction50%
๐Project Metrics
TDLR #TABS2025005831$57.0M
Project Value
195,000
Square Feet
$292/sqft
Cost/SqFt
10 months
Duration
Registered:Nov 18, 2024
Start:Aug 10, 2024
Target:Jun 9, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Tenant fit out of approximately 195,000 sf of administrative and data hall spaces including renovations to existing building entrance and loading docks, office spaces, data hall computer rack and technology and electrical distribution.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 18, 2024
Construction Start
August 10, 2024
Expected Completion
June 9, 2025
๐Related Projects
๐คSame Owner
$230.9M totalProperty Owner
๐ค
Compass Datacenters
Contact: Carter Brown
4 projects ยท $230.9M
14555 Dallas Pkwy Suite 125, Dallas, Texas 75254