๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Pinn Rd Shared Use Path
300 FT N of Brownleaf Dr to Marbach Rd, San Antonio, TX, 78227
Construction50%
๐Project Metrics
TDLR #TABS2025007660$1.1M
Project Value
40,113
Square Feet
$26/sqft
Cost/SqFt
11 months
Duration
Registered:Dec 13, 2024
Start:Apr 21, 2025
Target:Mar 5, 2026
Remaining:85 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construct shared use path (SUP) along Pinn Road on east side of the road.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 13, 2024
Review Complete
December 13, 2024
Construction Start
April 21, 2025
Expected Completion
March 5, 2026
Property Owner
๐ค
City of San Antonio
Contact: Eric Salazar, P.E.
6 projects ยท $17.9M
100 W Houston St, San Antonio, Texas 78205
Design Firm
๐๏ธ
Sanchez Salazar & Associates, LLC