๐Project Registered๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
NDSISD - Band Hall
1373 US HIGHWAY 259 S, Diana, TX, 75640
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025008291$2.4M
Project Value
9,500
Square Feet
$253/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Dec 20, 2024
Start:Apr 1, 2025
Target:Sep 30, 2026
Remaining:294 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
5,500 SF of Interior renovations to the Band Hall, a 4,000 SF addition, and associated site work including parking, site walks, and landscaping.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 20, 2024
Construction Start
April 1, 2025
Expected Completion
September 30, 2026
๐Related Projects
๐คBy Owner
$18.8M totalProperty Owner
๐ค
NEW DIANA ISD
Contact: MARSHALL MOORE
3 projects ยท $18.8M
1373 US HIGHWAY 259 S, Diana, Texas 75640
Design Firm
๐๏ธ
Pfluger Architects
6 projects ยท $28.8M
603 Munger Ave Ste 130, Dallas, Texas 75202