๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
QUINLAN COMMUNITY PARK
315 TX-35 BUS, Quinlan, TX, 75474
Construction50%
๐Project Metrics
TDLR #TABS2025008327$500K
Project Value
65,340
Square Feet
$8/sqft
Cost/SqFt
4 months
Duration
Registered:Dec 20, 2024
Start:Feb 1, 2025
Target:Jun 1, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction of existing pathway, pickleball courts and outdoor workout equipment.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 20, 2024
Review Complete
December 20, 2024
Construction Start
February 1, 2025
Expected Completion
June 1, 2025