๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
BTS Facility Daikin HVAC
300 West Elms Road, Killeen, TX, 76542
Construction50%
๐Project Metrics
TDLR #TABS2025008551$17.5M
Project Value
45,026
Square Feet
$389/sqft
Cost/SqFt
9 months
Duration
Registered:Dec 30, 2024
Start:Feb 1, 2025
Target:Oct 15, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New construction; Office / Warehouse
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 30, 2024
Review Complete
December 30, 2024
Construction Start
February 1, 2025
Expected Completion
October 15, 2025
๐Related Projects
๐๏ธBy Design Firm
$19.0M totalProperty Owner
๐ค
INDUSTRIAL RESERVE
Contact: Justin Toon
12404 PARK CENTRAL DR. SUITE 25, Dallas, Texas 75251
Design Firm
๐๏ธ
Seitz Architects, Inc.
2 projects ยท $19.0M
506 Meadowlake Lane, Heath, Texas 75032