๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Huntwick Ave - S. Staples to Pavement change
5500 Huntwick Ave to Pavement change, Corpus Christi, TX, 78413
Construction50%
๐Project Metrics
TDLR #TABS2025009040$1.3M
Project Value
5,000
Square Feet
$265/sqft
Cost/SqFt
7 months
Duration
Registered:Jan 8, 2025
Start:Mar 17, 2025
Target:Oct 3, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Approx. 5,000 SF of concrete sidewalk & ADA curb ramps
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 8, 2025
Review Complete
January 8, 2025
Construction Start
March 17, 2025
Expected Completion
October 3, 2025
Property Owner
๐ค
City of Corpus Christi
Contact: Mai-Theresa Bernal, P.E.
6 projects ยท $15.2M
1201 Leopard Street, Corpus Christi, Texas 78401
Design Firm
๐๏ธ
Munoz Engineering
6 projects ยท $14.2M