๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Elliott Electric Supply Bryan
10099 State Hwy 30, Bryan, TX, 77845
Construction50%
๐Project Metrics
TDLR #TABS2025009500$2.5M
Project Value
29,507
Square Feet
$85/sqft
Cost/SqFt
10 months
Duration
Registered:Jan 14, 2025
Start:Apr 1, 2025
Target:Jan 30, 2026
Remaining:51 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New metal building warehouse and office for Elliott Electric
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 14, 2025
Review Complete
January 14, 2025
Construction Start
April 1, 2025
Expected Completion
January 30, 2026
Property Owner
๐ค
Elliott Electric Supply
Contact: Jacob Chumley
5 projects ยท $20.8M
2526 N. Stallings Dr., Nacogdoches, Texas 75964
Design Firm
๐๏ธ
Element Architects
6 projects ยท $23.4M
1250 Wood Branch Park Dr Suite 480, Houston, Texas 77095