๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Horseshoe Lake Camp
8990 FM 787, Cleveland, TX, 77327
Construction50%
๐Project Metrics
TDLR #TABS2025009733$3.5M
Project Value
35,000
Square Feet
$100/sqft
Cost/SqFt
9 months
Duration
Registered:Jan 16, 2025
Start:Apr 1, 2025
Target:Dec 31, 2025
Remaining:21 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Not For Profit Church Camp including a Chapel, Cafeteria, 4 Bunks and Owners Residence
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 16, 2025
Review Complete
January 16, 2025
Construction Start
April 1, 2025
Expected Completion
December 31, 2025