๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
City of Celina Southeast Pump Station
1100 Old Glendenning Rd, Celina, TX, 75009
Construction50%
๐Project Metrics
TDLR #TABS2025009739$69.6M
Project Value
10,012
Square Feet
$6956/sqft
Cost/SqFt
2y 4mo
Duration
Registered:Jan 16, 2025
Start:Jun 11, 2025
Target:Sep 28, 2027
Remaining:657 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New city fresh water pump station.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 16, 2025
Review Complete
January 16, 2025
Construction Start
June 11, 2025
Expected Completion
September 28, 2027
Property Owner
๐ค
City of Celina
Contact: Linda Majeed, P.E., CFM
6 projects ยท $90.0M
300 W. Maple Street, Celina, Texas 75009
Design Firm
๐๏ธ
Freese and Nichols
6 projects ยท $121.3M
12770 Merit Drive, Suite 900, Dallas, Texas 75251