MVISD Middle School #3
W. Montgomery and Straus Medina, Medina, TX, 78252
Construction50%
๐Project Metrics
TDLR #TABS2025009962$80.7M
Project Value
172,284
Square Feet
$469/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Jan 21, 2025
Start:Apr 17, 2025
Target:Apr 23, 2027
Remaining:499 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New 1200 student Middle School building for Medina Valley ISD.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 21, 2025
Review Complete
January 21, 2025
Construction Start
April 17, 2025
Expected Completion
April 23, 2027
๐Related Projects
๐คBy Owner
$94.7M totalProperty Owner
๐ค
Medina Valley ISD
Contact: Amy Routh
2 projects ยท $94.7M
8752 FM 471 South, LaCoste, Texas 78039
Design Firm
๐๏ธ
VLK Architects
6 projects ยท $65.0M
250 West Nottingham Drive, Suite 115, San Antonio, Texas 78209