๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Gulf Inland B.P. Pump House
1500 Rolke Rd, Dayton, TX, 77535
Construction50%
๐Project Metrics
TDLR #TABS2025010527$607K
Project Value
500
Square Feet
$1214/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Jan 28, 2025
Start:Mar 31, 2025
Target:Sep 30, 2026
Remaining:294 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New utility building to house fire sprinkler pump
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 28, 2025
Review Complete
January 28, 2025
Construction Start
March 31, 2025
Expected Completion
September 30, 2026
๐Related Projects
Property Owner
๐ค
Clay Development & Construction
Contact: Joy Rosencutter
6 projects ยท $41.1M
1244 N Post Oak Rd, Ste 200, Houston, Texas 77055
Design Firm
๐๏ธ
Clay Development & Construction
6 projects ยท $36.5M
1244 N Post Oak Rd, Ste 200, Houston, Texas 77055