๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SL 12 (CSJ: 0581-01-182)
From: South of John West To: Tillman Street, Dallas, TX, 75227
Construction50%
๐Project Metrics
TDLR #TABS2025010735$506K
Project Value
5,586
Square Feet
$91/sqft
Cost/SqFt
7 months
Duration
Registered:Jan 30, 2025
Start:Aug 1, 2025
Target:Mar 1, 2026
Remaining:81 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Installation of traffic signals.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 30, 2025
Review Complete
January 30, 2025
Construction Start
August 1, 2025
Expected Completion
March 1, 2026
Property Owner
๐ค
TxDOT District: Dallas
Contact: Nathan Petter, P.E.
6 projects ยท $5.6M