๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SH 27 (CSJ: 0142-06-029)
From: US 87 To: Kendall/Kerr County Line, Comfort, TX, 78013
Completed100%
๐Project Metrics
TDLR #TABS2025010788$80K
Project Value
2,651
Square Feet
$30/sqft
Cost/SqFt
11 months
Duration
Registered:Jan 31, 2025
Start:Mar 1, 2024
Target:Feb 1, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Base repair, mill, inlay and pavement markings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 31, 2025
Project Closed
January 31, 2025
Construction Start
March 1, 2024
Expected Completion
February 1, 2025
Property Owner
๐ค
TxDOT District: San Antonio
Contact: Ron Jones, P.E.
6 projects ยท $5.4M
4615 NW Loop 410, San Antonio, Texas 78229
Design Firm
๐๏ธ
Kimley-Horn
6 projects ยท $59.4M
10101 Reunion Place, Suite 400, San Antonio, Texas 78216