River Ranch Phase 5 South Landscape Improvements
River Run Trail & Timberland Ranch Road, Dayton, TX, 77535
Construction50%
๐Project Metrics
TDLR #TABS2025011599$2.0M
Project Value
490,000
Square Feet
$4/sqft
Cost/SqFt
11 months
Duration
Registered:Feb 11, 2025
Start:Apr 1, 2025
Target:Feb 27, 2026
Remaining:79 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Concrete Walk, Planting, Irrigation, Fine Grade and Hydromulch
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 11, 2025
Review Complete
February 11, 2025
Construction Start
April 1, 2025
Expected Completion
February 27, 2026
๐Related Projects
๐คBy Owner
$3.2M total๐๏ธBy Design Firm
$6.1M totalLago Mar POD 10 Section 3 Landscape Improvements
Texas Cityยท$499K
Mavera Sections 11, 12, 14 and Large Lake Landscape Improvements
Conroeยท$2.4M
Holly Ridge Phase 1 Landscape Improvements
Rosenbergยท$784K
Meadows at Imperial Oaks Sections 24 and 25 Landscape Improvements
Conroeยท$320K
Property Owner
๐ค
River Ranch One Investments, Ltd.
Contact: Harrison Bibb
2 projects ยท $3.2M
5851 San Felipe Blvd, Suite 800, Houston, Texas 77057
Design Firm
๐๏ธ
KGA DeForest Design, LLC
6 projects ยท $6.1M
24275 Katy Freeway #300, Katy, Texas 77494