📝Review Complete🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
PAC Hydronic Piping Replacement
1400 W Villaret Blvd., San Antonio, TX, 78224
Construction50%
📊Project Metrics
TDLR #TABS2025011631$123K
Project Value
30,799
Square Feet
$4/sqft
Cost/SqFt
9 months
Duration
Registered:Feb 11, 2025
Start:Jan 1, 2025
Target:Oct 1, 2025
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Chill water pipes replacement with sidewalk, removal & replacement.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 11, 2025
Review Complete
February 11, 2025
Construction Start
January 1, 2025
Expected Completion
October 1, 2025