๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Northside ISD | John C. Holmgreen Center - Security Upgrades
8580 Ewing Halsell Drive, San Antonio, TX, 78229
Construction50%
๐Project Metrics
TDLR #TABS2025011690$150K
Project Value
900
Square Feet
$167/sqft
Cost/SqFt
2 months
Duration
Registered:Feb 11, 2025
Start:Jun 9, 2025
Target:Aug 8, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Northside ISD | John C. Holmgreen Center - Security Upgrades
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 11, 2025
Review Complete
February 11, 2025
Construction Start
June 9, 2025
Expected Completion
August 8, 2025
๐Related Projects
๐คBy Owner
$35.1M totalAdministration & Classroom Replacement at John Marshall High School
San Antonioยท$20.0M
Northside ISD | Nellie M. Reddix Center - Security Upgrades
San Antonioยท$150K
Paving Upgrades at Earl Warren HS
San Antonioยท$1.6M
Paving Upgrades at Virginia A. Myers Elementary School
San Antonioยท$533K
Property Owner
๐ค
Northside ISD
Contact: James Evans
6 projects ยท $35.1M
5900 Evers Road Building C, San Antonio, Texas 78238
Design Firm
๐๏ธ
Huckabee
6 projects ยท $20.6M
9830 Colonnade Blvd. Ste. 130, San Antonio, Texas 78230