๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Dorsey Street (from Garnett to Moursund Blvd)
Dorsey Street, San Antonio, TX, 78221
Construction50%
๐Project Metrics
TDLR #TABS2025011772$195K
Project Value
132,000
Square Feet
$1/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Feb 12, 2025
Start:Aug 1, 2025
Target:Dec 1, 2026
Remaining:356 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction of Dorsey Street from Garnett to Moursund. To include road widening, new curb & gutter, sidewalk, underground storm system, and utility replacement. Approximately 2,200 linear feet.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 12, 2025
Review Complete
February 12, 2025
Construction Start
August 1, 2025
Expected Completion
December 1, 2026
Property Owner
๐ค
City of San Antonio
Contact: Florencio Rodriguez, Jr., PE
6 projects ยท $17.9M