๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Thorndale High School
100 Stadium Street, Thorndale, TX, 76577
Construction50%
๐Project Metrics
TDLR #TABS2025011778$24.0M
Project Value
54,000
Square Feet
$444/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Feb 12, 2025
Start:May 1, 2025
Target:Jul 5, 2026
Remaining:207 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
new construction of a single story 54,000 square foot high school. a portion of the site will be developed for parking, bus drop off, kitchen/ band loading areas.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 12, 2025
Review Complete
February 12, 2025
Construction Start
May 1, 2025
Expected Completion
July 5, 2026
Property Owner
๐ค
THORNDALE HIGH SCHOOL - TISD
Contact: ZACK KLEYPAS
300 S MAIN STREET, THORNDALE, Texas 76577