📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Colton - Trails
Intersection of Permian Parkway & El Pino Street, Todd Mission, TX, 77316
Construction50%
📊Project Metrics
TDLR #TABS2025012543$775K
Project Value
1
Square Feet
$775000/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Feb 24, 2025
Start:Feb 10, 2025
Target:Aug 15, 2026
Remaining:248 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
asphalt trails
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 24, 2025
Review Complete
February 24, 2025
Construction Start
February 10, 2025
Expected Completion
August 15, 2026