๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Phase 14B Street Reconstruction

Bogard Drive/Dunn Drive; Lamar Street; Kean Circle, The Colony, TX, 75056
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025012748
$4.5M
Project Value
27,622
Square Feet
$161/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Feb 25, 2025
Start:Feb 15, 2025
Target:Mar 22, 2026
Remaining:102 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

econstruction of roadways, sidewalks with barrier free ramps, driveways, and utilities on three streets. Total SF of sidewalk removal/replacement = 27,622 SF; BFR removal/replacement = 1,970 SF.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 25, 2025
Review Complete
February 25, 2025
Construction Start
February 15, 2025
Expected Completion
March 22, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025012748

Property Owner

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
MARCELA ABADI,RHOADS
RAS #240
7516 DANFIELD CT, DALLAS, TX 75252