✅Inspection Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Parad Ice
3427 S Osage, Amarillo, TX, 79118
Final Inspection85%
📊Project Metrics
TDLR #TABS2025012789$50K
Project Value
1,800
Square Feet
$28/sqft
Cost/SqFt
4 months
Duration
Registered:Feb 26, 2025
Start:Mar 15, 2025
Target:Jun 30, 2025
✅
Inspection Complete
Final inspection completed, awaiting project closure
📋Scope of Work
remodel work for a ice cream shop
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 26, 2025
Inspection Complete
February 26, 2025
Construction Start
March 15, 2025
Expected Completion
June 30, 2025