๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Waco City Secretary Office Reno
300 Austin AVE, Waco, TX, 76701
Completed100%
๐Project Metrics
TDLR #TABS2025013183$120K
Project Value
1,110
Square Feet
$108/sqft
Cost/SqFt
2 months
Duration
Registered:Mar 3, 2025
Start:Apr 16, 2025
Target:Jun 18, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Level 2 alterations and repairs to City Secretary offices at Waco City Hall.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 3, 2025
Project Closed
March 3, 2025
Construction Start
April 16, 2025
Expected Completion
June 18, 2025
๐Related Projects
๐Nearby Projects
Within 1 kmRenovations to the Taylor Museum Annex
724 N. 8th Streetยท$248K
Waco Street Rehabilition District 3
Various Streets in District 3, 300 Austin Streetยท$186K
City of Waco Street Rehabilitation District 5
300 Austin Avenueยท$325K
Waco Downtown Redevelopment Infrastructure, Phase 1A
4th St, 3rd St, Jefferson Ave, University Parks Dr Columbus Ave., Washington Ave.ยท$75.0M
Property Owner
๐ค
City of Waco, Facilities Department
Contact: Shelley Butler
311 Colcord Ave, Waco, Waco, Texas 76707