๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Brakes Plus
SWC of I-30 and Tower Road, Fate, TX, 75132
Construction50%
๐Project Metrics
TDLR #TABS2025013246$1.5M
Project Value
4,950
Square Feet
$303/sqft
Cost/SqFt
10 months
Duration
Registered:Mar 4, 2025
Start:May 5, 2025
Target:Mar 1, 2026
Remaining:81 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Ground up construction of an auto service facility with associated site work.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 4, 2025
Review Complete
March 4, 2025
Construction Start
May 5, 2025
Expected Completion
March 1, 2026