McGregor Replacement Junior High School
1 Dell Way, Mcgregor, TX, 76657
Construction50%
๐Project Metrics
TDLR #TABS2025013253$41.0M
Project Value
101,500
Square Feet
$404/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Mar 4, 2025
Start:May 1, 2025
Target:Aug 1, 2026
Remaining:234 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
45,000 SF renovation of existing building, 60,000 SF of new construction converting an existing building into a new Junior High School for 600 students for McGregor ISD.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 4, 2025
Review Complete
March 4, 2025
Construction Start
May 1, 2025
Expected Completion
August 1, 2026