📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Crawford Road Project
4305 Crawford Road, Spicewood, TX, 78669
Construction50%
📊Project Metrics
TDLR #TABS2025013507$1.9M
Project Value
11,708
Square Feet
$162/sqft
Cost/SqFt
9 months
Duration
Registered:Mar 6, 2025
Start:May 12, 2025
Target:Feb 9, 2026
Remaining:61 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Sports Complex
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
March 6, 2025
Review Complete
March 6, 2025
Construction Start
May 12, 2025
Expected Completion
February 9, 2026