๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
The Bluffs at Blackhawk Sections 1 - 4
Intersection of Melber Lane and CR 198, Hutto, TX, 78634
๐Project Overview
$442K
Est. Cost
517,577
Square Feet
1 year
Duration
211
Days Left
๐Scope of Work
2,897 LF of 5' concrete sidewalk, 5,452 LF of 6' concrete sidewalk, and 76 Type 1 Ramps. Total of 51,757sf (including ramps).
๐ Project Timeline
Registered
March 11, 2025
Review Complete
March 11, 2025
Construction Start
June 30, 2025
Expected Completion
June 30, 2026
๐บ๏ธLocation
๐Related Projects
๐๏ธMore by ALM Engineering, Inc. F-3565
Property Owner
๐ค
Tiemann Land and Cattle Development, Inc.
Contact: Sam Fenwick
21100 Carries Ranch Rd., Pflugerville, Texas 78660
512-990-1933
Design Firm
๐๏ธ
ALM Engineering, Inc. F-3565
2 total projects
PO Box 536, Dripping Springs, Texas 78620
512-431-9600
Registered Specialist
๐
ELAINE K,ANDERSEN
RAS #1284
PO BOX 143214, AUSTIN, TX 78714