๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Entertainment District Sidewalks Phase 2

W. Abram St, 101, Arlington, TX, 76010
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025014174
$901K
Project Value
72,387
Square Feet
$12/sqft
Cost/SqFt
10 months
Duration
Registered:Mar 13, 2025
Start:May 26, 2025
Target:Mar 26, 2026
Remaining:106 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

To fill in sidewalk gaps within the Entertainment District at Various locations. 72,387SF

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 13, 2025
Review Complete
March 13, 2025
Construction Start
May 26, 2025
Expected Completion
March 26, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025014174

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
GEORGE A,PATTERSON
RAS #503
5302 NORMA, FORT WORTH, TX 76112