Circle K - Hwy 114 & Mustang
1307 E. Hwy 114, Levelland, TX, 79336
Construction50%
๐Project Metrics
TDLR #TABS2025014243$5.5M
Project Value
8,682
Square Feet
$633/sqft
Cost/SqFt
7 months
Duration
Registered:Mar 14, 2025
Start:Aug 18, 2025
Target:Mar 5, 2026
Remaining:85 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of a New Circle K Convenience Store and Fueling Station
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 14, 2025
Review Complete
March 14, 2025
Construction Start
August 18, 2025
Expected Completion
March 5, 2026
Property Owner
๐ค
Circle K Stores Inc.
Contact: Jasmine Reed
6 projects ยท $34.7M
17319 San Pedro Ave. Suite 400, Bldg 4, San Antonio, Texas 78232
Design Firm
๐๏ธ
Core States Group
6 projects ยท $18.8M
111 3rd Ave S. Suite 400, Minneapolis, Minnesota 55401