๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
HFI Capital - Pinnacle Industrial Center
695 Mercury Mine Road, Laredo, TX, 78045
Construction50%
๐Project Metrics
TDLR #TABS2025014482$18.0M
Project Value
335,400
Square Feet
$54/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Mar 18, 2025
Start:Apr 11, 2025
Target:May 29, 2026
Remaining:170 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New shell Warehouse with 335,400 SF.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 18, 2025
Review Complete
March 18, 2025
Construction Start
April 11, 2025
Expected Completion
May 29, 2026