๐Project Registered๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Pitstop Express
4504 Yale St. at W. Whitney St., Houston, TX, 77018
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025015047$863K
Project Value
9,056
Square Feet
$95/sqft
Cost/SqFt
5 months
Duration
Registered:Mar 25, 2025
Start:Oct 31, 2025
Target:Mar 31, 2026
Remaining:111 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
New Gas Station with Fuel Canopy
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 25, 2025
Construction Start
October 31, 2025
Expected Completion
March 31, 2026
๐Related Projects
๐๏ธBy Design Firm
$3.5M totalProperty Owner
๐ค
Encore Capital, LLC
Contact: Imran Dhanani
322 Julie Rivers Dr., Sugar Land, Texas 77478
Design Firm
๐๏ธ
Interplan Associates, Inc.
3 projects ยท $3.5M
19855 Greenwind Chase Dr, Houston, Texas 77094