๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

KISD Wunderlich Intermediate School Renovations

11800 Misty Valley Drive, Houston, TX, 77066
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025015235
$37.0M
Project Value
165,400
Square Feet
$224/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Mar 27, 2025
Start:Jun 2, 2025
Target:Jul 31, 2026
Remaining:233 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Major renovations to Wunderlich Intermediate School, including interior and reconfiguration, life safety upgrades, and building additions.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 27, 2025
Review Complete
March 27, 2025
Construction Start
June 2, 2025
Expected Completion
July 31, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025015235

Design Firm

๐Ÿ›๏ธ
BRW Architects, Inc.
2 projects ยท $37.5M
4501 Magnolia Cove Drive Suite 250, Houston, Texas 77345

Registered Accessibility Specialist

๐Ÿ“‹
LAURA,FULKERSON
RAS #96
PO BOX 2008, MASON, TX 76856