๐Ÿ“Review Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Marlin ISD High School Gym Addition

1400 Capps Street, Marlin, TX, 76661
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025015541
$5.9M
Project Value
13,800
Square Feet
$428/sqft
Cost/SqFt
1 year
Duration
Registered:Apr 1, 2025
Start:Apr 30, 2025
Target:Apr 30, 2026
Remaining:141 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

13800 SF PEMB addition to match the existing building to include gymnasium area with spectator seating and entry vestibule.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 1, 2025
Review Complete
April 1, 2025
Construction Start
April 30, 2025
Expected Completion
April 30, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025015541

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
JOSEPH,HUSBAND
RAS #27
1108 LAVACA STREET STE 110-313, AUSTIN, TX 78701