๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
ECISD Transportation Facility
Highway 87 East, Past the Beck Rd., San Antonio, TX, 78263
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025016419$11.0M
Project Value
16,200
Square Feet
$679/sqft
Cost/SqFt
10 months
Duration
Registered:Apr 10, 2025
Start:Jul 28, 2025
Target:Jun 1, 2026
Remaining:173 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
NEW CONSTRUCTION TRANSPORTATION FACILITY. SITE WILL BE DEVELOPED AND PAVED FOR BUS PARKING. THE SITE WILL ALSO HAVE A FUEL STATION AND BUS WASH STATION. THE ADMINISTRATIVE BUILDING IS A ONE STORY METAL BUILDING THAT WILL HOUSE OFFICES, CONFERENCE
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 10, 2025
Construction Start
July 28, 2025
Expected Completion
June 1, 2026
๐Related Projects
๐คBy Owner
$191.0M totalProperty Owner
๐ค
East Central Independent School District
Contact: John Thomas
2 projects ยท $191.0M
6634 Sulphur Springs Rd., San Antonio, Texas 78263
Design Firm
๐๏ธ
LPA, Inc.
4 projects ยท $18.0M
1811 S Alamo St UNIT 100, San Antonio, Texas 78204