Wilson Creek Park Phase I
2100 E Sunset Blvd, Celina, TX, 75009
Construction50%
๐Project Metrics
TDLR #TABS2025016927$12.2M
Project Value
1,698,840
Square Feet
$7/sqft
Cost/SqFt
1 year
Duration
Registered:Apr 17, 2025
Start:Jul 1, 2025
Target:Jul 1, 2026
Remaining:203 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Lighted Multi-Use Field Areas, Prefabricated Restroom Concession Building, Parking Lot/Drives, Pedestrian Trails, Landscaping and Irrigation. Disturbed area in Phase 1 is approx. 39Acres. Includes irrigation pond
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 17, 2025
Review Complete
April 17, 2025
Construction Start
July 1, 2025
Expected Completion
July 1, 2026
Property Owner
๐ค
City of Celina
Contact: Steve Walsh
6 projects ยท $90.0M
300 W. Maple, celina, Texas 75009